• Home
  • Media
  • Newsletters
  • Policies
  • North Sydney Council
  • Home
  • Media
  • Newsletters
  • Policies
  • North Sydney Council

Newsletter 74 – Pool Cost and Delay

  • Posted by IanMuttonAdmin
  • On May 3, 2026

Newsletter Number 74 – May 2026

North Sydney’s Olympic Pool.

  • Why the delays in completion? Now 3 years late
  • What’s the cost? Now (“at least”) 90% over “budget”
  • Why “at least”? Because we don’t know the final cost

Who has lead Council through the Pool project?

Consider the number of months:

  • Between signing contract (January 2021) and projected to be completed in May 2026 = 63
  • J Gibson was mayor = 9
  • mayor’s position vacant = 3
  • M Baker was and remains mayor = 53.

Background

The decision was taken in 2020 to go ahead with the rebuild of the pool and grandstand – refurbishment was simply not a viable option.

  • The pool liner installed a decade ago to stop leaking was progressively failing.
  • The grandstand was suffering concrete cancer and had its capacity reduced because of safety fears.

The contract for the design:

  • The architect asserted that a full set of final drawings and documents had been provided.

The contract for the rebuild:

  • is based on the Australian Standard AS4000-1997 Construction Contract modified for the rebuild project,
  • was put out to tender,
  • attracted 5 non-conforming bids,
    • negotiations with a bidder concluded with Council’s executive recommending the contract be given to one bidder – that recommendation was accepted by Council in December 2020,
    • The negotiation resulted in the budget allocation of $63.9M, and
  • was signed in January 2021.

The tender process was reported on by a probity advisor. The report was fulsome and complimentary.

In March 2021 the Olympic Pool site was handed over to the builder.

With the (design and construct) contracts in place the task of North Sydney Council was to administer those contracts.

Construction – delays and escalating cost

Council to November 2021 under Mayor Gibson

Date of Report

Estimated Cost Increase

Estimated date for Completion

2020 – December

$64m

2022 – January

2021 – October

$64.2m*

2023 – March

*Outstanding variations reported to be with in the contingency allowance.

New Council and Mayor Baker elected

The Councillors elected in December 2021 elected Zoe Baker mayor in January 2022

Does Mayor Baker, now in control:

  • Seek to renegotiate the contract for the rebuild of the pool? No
  • Change the lawyers who advised on and were engaged in the negotiation of the contract for the rebuild? No
  • Change the architects who designed the rebuild? No

The inaction was a validation of the appropriateness of contracts and an endorsement of their past administration.

Date of Report

Estimated Cost Increase

Estimated date for Completion

2022 – June

$64m + $8m

2023 – July

2022 – August

$64m + $9m

2023 – December

2022 – October

$64m + $20m

2023 – November

2023 – April *

$64m + $25m to $30m

2024 – April

2024 – December

Total over $122m

2025 – July

2025 – April

Total over $122m

2025 – August

2025 – October

Total over $122m

2025 – December

2025 – December

Total over $122m

2026 – January

2026 – March

Total over $122m

2026 – mid April

*The potential budget over run was reported at between $25 and $30m with the scope expanded to include

  • consultants, contract works, works outside original scope such as fit outs and technology and costs associated with establishing operations for the pools, gym, creche, and kiosk
    • Significantly, the decision to bring management in-house shifted full operational risk to Council and added significant cost, beyond fit-out, approximately $1 million per annum to which is to be added depreciation estimated to be an additional $2.4m pa
  • “sufficient” contingency given the level of risk associated with the project.

The forecast total cost then escalated to $122m by the:

  • decision of Council to fit out and operate the amenities (e.g. gymnasium, swim school and retail) which were originally planned to be let out to independent operators,
  • litigation with the builder and architect, and
  • delays (which on any building project are costly).

Eight months into Mayor Baker’s term

On 10 October 2022 Council resolved to undertake an independent review of the Council’s management of the project.

PricewaterhouseCoopers (PWC)was engaged to undertake the review – it’s made 16 “findings” and 33 recommendations (13 specific to the Pool Project).

Significantly, PwC did not recommend contracting out project management, opting instead, for Council to continue to manage the project (albeit with the added support of a new “steering committee” with APP Corporation engaged at first as an Independent Advisor – now at a cost of $2m).

  • In other words, the advice was to better administer the contracts.

Now over 3 years late the cost to complete (using the estimate given by Council in February 2024) has risen, 90% since Mayor Baker assumed control

 

 18

0 Comments

**Open Letter to F Wilson re bikeways
Recent Posts
  • Newsletter 76 – Henry Lawson Parade
  • Newsletter 75 – Cammeray Golf Course
  • Newsletter 74 – Pool Cost and Delay
  • Newsletter 73 – Rates and IPART
  • Newsletter 72 – Code of Meeting Practice
Archives
  • May 2026
  • March 2026
  • December 2025
  • November 2025
  • April 2025
  • February 2025
  • December 2024
  • June 2024
  • April 2024
  • November 2023
  • October 2023
  • August 2023
  • June 2023
  • May 2023
  • April 2023
  • March 2023
  • February 2023
  • December 2022
  • October 2022
  • May 2022
  • April 2022
  • March 2022
  • January 2022
  • December 2021
  • September 2021
  • August 2021
  • July 2021
  • June 2021
  • May 2021
  • January 2021
  • September 2020
  • April 2020
  • March 2020
  • January 2020
  • August 2019
  • February 2019
  • December 2018
  • October 2018
  • August 2018
  • July 2018
  • June 2018
Categories
  • Beaches Tunnel
  • Berry's Bay
  • Bradfield Park
  • buildings
  • Cammeray Golf Course
  • Council
  • Harbour Bridge Cycle Ramp
  • Harry's Park
  • high line
  • Land Rights
  • Luna Park
  • North Sydney Olympic Pool
  • Parking
  • Parks & Spaces
  • Roads
  • Sydney Harbour High Line
  • Uncategorized
  • Watts Park
  • Waverton Bowling Club

Newsletter 73 - Rates and IPART

Previous thumb

Newsletter 75 - Cammeray Golf Course

Next thumb
Scroll
@2021 Ian Mutton - A voice for North Sydney. Authorised by Ian Mutton of 2 Dind Street, Milsons Point, NSW 2061. Telephone +61 4 1627 0022