• Home
  • Media
  • Newsletters
  • Policies
  • North Sydney Council
  • Home
  • Media
  • Newsletters
  • Policies
  • North Sydney Council

Newsletter 40 –  Pool Update

  • Posted by IanMuttonAdmin
  • On January 10, 2022

North Sydney’s Olympic Pool – is it on “time” and “budget”?

 

It was a year ago that I wrote on the pool – https://www.ianmutton.com/2021/01/17/north-shore-community-newsletter-23-olympic-pool/ . With a newly elected council it’s time for an update.

Background

The decision was taken in 2020 to go ahead with the rebuild of the pool

The contract for the rebuild:

  • Is based on the Australian Standard AS4000-1997 Construction Contract modified for the rebuild project; and
  • was then put out to tender.

The tender process was reported on by a probity advisor. The report was fulsome and complimentary.

The contract was awarded at the start of this year.

Council reported in December 2021:

The entire budget allocation, including the design phase, consultation, DA preparation, construction and an allowance for contingencies has increased from $57.9M to $63.9M.

The increase occurred after obtaining competitive tenders and adjusting for risk factors associated with construction on the edge of the harbour.

The budget allocution has not changed since reported in December 2021.

The challenge is to bring the project in on time, within budget and resist scope changes that add to the cost or reduce the amenity.

The last report to council was made in October 2021 (at the last substantive meeting before the election). The report was comprehensive; it included details of all claims for (a) extension of time to complete and (b) variation (accepted and pending), as well as details of funds applied and scope changes. Because the report included strategies for the negotiations with the contractor, most notably on variations, it was received by councillors in “confidential” session.

Time for completion (construction commencement date of 9 March 2021 with a contracted completion date of 14 November 2022.

  • Variations to the timeline total 60 days – with nearly one third attributed to COVID and weather-related factors and the balance to the removal of hazardous materials (notably asbestos).

Variations impacting on budget – Approved variations are, given the size of the project, small – less than $200,000. Unapproved claims for variations (at values attributed by council) are within the amount allowed for contingencies.

  • The challenges for council are to minimise the exposure to claims for variations and critically appraise those that are made.

Scope changes are minor.

The project is large and complex – it requires tight management to prevent cost over runs.

We councillors will ultimately be judged by our constructive involvement with the delivery of the project – the need is to understand of the reports and not just rely on the summaries provided by others.

 

Ian Mutton

 

 13
  •  " target="_blank">

0 Comments

**Open Letter to F Wilson re bikeways
Recent Posts
  • Newsletter 68 – Community Strategic Plan
  • Newsletter 67 – Crisis! What Crisis
  • Newsletter 66 – Rates
  • Newsletter 64 – North Sydney Olympic Pool
  • Newsletter 63 – Bradfield Park
Archives
  • April 2025
  • February 2025
  • December 2024
  • June 2024
  • April 2024
  • November 2023
  • October 2023
  • August 2023
  • June 2023
  • May 2023
  • April 2023
  • March 2023
  • February 2023
  • December 2022
  • October 2022
  • May 2022
  • April 2022
  • March 2022
  • January 2022
  • December 2021
  • September 2021
  • August 2021
  • July 2021
  • June 2021
  • May 2021
  • January 2021
  • September 2020
  • April 2020
  • March 2020
  • January 2020
  • August 2019
  • February 2019
  • December 2018
  • October 2018
  • August 2018
  • July 2018
  • June 2018
Categories
  • Beaches Tunnel
  • Berry's Bay
  • Bradfield Park
  • buildings
  • Council
  • Harbour Bridge Cycle Ramp
  • Harry's Park
  • high line
  • Land Rights
  • Luna Park
  • North Sydney Olympic Pool
  • Parking
  • Parks & Spaces
  • Roads
  • Sydney Harbour High Line
  • Uncategorized
  • Watts Park
  • Waverton Bowling Club

Newsletter 39 -  Protecting Our Parklands

Newsletter 41 -  The State Government v Open Green Space

Next thumb
Scroll
@2021 Ian Mutton - A voice for North Sydney. Authorised by Ian Mutton of 2 Dind Street, Milsons Point, NSW 2061. Telephone +61 4 1627 0022